Take the 2-minute tour ×
Software Quality Assurance & Testing Stack Exchange is a question and answer site for software quality control experts, automation engineers, and software testers. It's 100% free, no registration required.

We are using HPQC on our project. I am new to the tool. I have an Excel sheet with the test plan ID and their related requirement IDs. The manual process is very time consuming.

How do I automate the linking of the requirement IDs with the corresponding test plan ID?

share|improve this question
add comment

1 Answer 1

There are 2 plugins:

  1. Plugin to export requirements from word document to QC
  2. Plugin to export requirements from excel document to QC

Once you install these in your machine, you will get options to 'export to QC' when you open the respective application.

The pre-requisite is to have a properly formatted document (either word or excel). It will contain your reqID and planID along with other fields. Now, once you run the plugin it will list the available fields in your QC requirement section. You can choose a field and map it to the respective column in your excel sheet. Finally, click upload.

Now, the fields available in your 'requirements' section (in QC) is entirely customizable. You may have to contact your QC Admin (or touch base with your HP point of contact) to ensure that those fields get listed when you use the plugin.

Link: http://update.external.hp.com/qualitycenter/qc100/index.html

share|improve this answer
add comment

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.