Is there a way when using test manager to stop a test part of the way through close down test manager and continue the run at a later date with the attachments you have taken?

share|improve this question
    
Out of curiosity why would you want to do this? Are you trying to use the test to generate data you would use in later tests? –  Dan Snell Feb 19 '13 at 21:42
    
Dan the reason for this is sometimes a more 'important' test needs to be run and would like to park one you are halfway through and then pick up later on. –  Teague Jun 5 '13 at 12:10
add comment

1 Answer 1

You can pause the test run, then save and close. All the attachments you've created to that point will be saved.

When you're ready to come back to the test, you'll need to return to the point you left and located the unfinished run (Test > Analyze Test Runs), then Resume.

You should be able to pick up where you left off.

share|improve this answer
add comment

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.