Skip to main content
30 events
when toggle format what by license comment
Oct 22, 2020 at 23:58 answer added anichols timeline score: 1
Oct 19, 2020 at 18:45 vote accept MarkThomas52
S Oct 14, 2020 at 4:51 history suggested Cave Johnson CC BY-SA 4.0
changed to better wording IMHO; remove capitalization from title
Oct 14, 2020 at 2:45 review Suggested edits
S Oct 14, 2020 at 4:51
Oct 13, 2020 at 22:01 answer added Robbie Goodwin timeline score: 0
Oct 13, 2020 at 11:20 comment added spikey_richie @dzieciou A PBI is a work item type on the CMMI template, think Feature and/or User Story in an Agile template.
S Oct 13, 2020 at 2:19 history suggested costrom CC BY-SA 4.0
Added PBI description to question; from comments
Oct 12, 2020 at 18:00 history tweeted twitter.com/StackSQA/status/1315713871169150977
Oct 12, 2020 at 16:19 review Suggested edits
S Oct 13, 2020 at 2:19
Oct 12, 2020 at 12:01 comment added Aaron F @davidbak "stories in subsequent sprints typically build on stories completed in earlier sprints" - in our case the new features always build on or replace existing features. We don't do new work on features which haven't yet been tested and rolled into a release. Maybe this is a luxury other teams don't have? (We're working on a live product and are doing incremental iterative updates... generally speaking we're adding support for new technologies and dropping support for obsolete ones) What works for us might not work for everyone else.
Oct 12, 2020 at 11:59 answer added pjc50 timeline score: 5
Oct 12, 2020 at 11:53 comment added Aaron F @davidbak The US won't be accepted and closed until the QA's done. Sometimes, depending on QA workload and priorities, a US will be put on hold for a sprint or two. If the feature is urgent, and the PO wants it, then it can go into the next release with minor bugs. I think the product makes a big difference, though: where I am, it's a global product with millions of concurrent users, so we take things very slowly in order to not break stuff; and, generally, developers are working on features that won't go into production for another 8 to 12 months. It's a large team and we do long sprints.
Oct 12, 2020 at 11:41 comment added Mr47 @dzieciou Product Backlog Item; basically an item on the 'todo list'.
Oct 12, 2020 at 10:59 answer added Graham timeline score: -1
Oct 12, 2020 at 8:30 answer added o.m. timeline score: 5
Oct 12, 2020 at 5:21 history edited JAINAM
edited tags
Oct 12, 2020 at 5:01 answer added JAINAM timeline score: 8
Oct 12, 2020 at 2:32 answer added Richard Hunter timeline score: 6
Oct 11, 2020 at 22:02 comment added davidbak @AaronF - How does this actually work? Can a story be accepted by the product owner when it has been "developed" but won't be tested for 2-3 sprints? What's the acceptance criteria? When some story fails QA 2 or 3 sprints later - and can't go into production - how is that addressed by the dev team? And then too, stories in subsequent sprints typically build on stories completed in earlier sprints - how does that work if the stuff from earlier sprints can't be relied on or is subject to change due to not working correctly?
Oct 11, 2020 at 21:58 comment added davidbak I've seen this before. It can be very demoralizing to the QA team, and frustrating for the product owners. Where I saw this - where there were 2 week sprints !! which contributed to the end-of-sprint dev rush - it was not solved but I always thought it could have been by staggering the dev and QA sprints - if there was some kind of enforcement mechanism where stuff that needed additional work to pass QA was addressed immediately by the devs even though it would impact their own (current) sprint. But maybe that doesn't work in practice either.
Oct 11, 2020 at 16:16 comment added Aaron F Then the QA work should not be done in the same sprint, and the planning should take this into account. Where I work, QA team are sometimes testing Dev team work from two or three sprints before the current one. What are your QA people doing for the rest of the sprint, before the developers are finished?
Oct 11, 2020 at 14:28 comment added dzieciou PBI? What is that?
Oct 11, 2020 at 14:16 answer added eckes timeline score: 1
Oct 11, 2020 at 12:56 history became hot network question
Oct 11, 2020 at 12:30 answer added Thomas Owens timeline score: 5
Oct 11, 2020 at 10:14 answer added Michael Durrant timeline score: 28
Oct 11, 2020 at 9:52 answer added pavelsaman timeline score: 5
Oct 11, 2020 at 7:59 comment added João Farias What are the reasons for your team to use sprints, rather than focus on continuous delivery, aimed at optimizing cycle time?
Oct 11, 2020 at 4:57 review First posts
Oct 11, 2020 at 9:08
Oct 11, 2020 at 4:55 history asked MarkThomas52 CC BY-SA 4.0