3

It's been my understanding that when using Test Lab in Quality Center, if changes are made within a script, i.e data/ criteria change those updates DO NOT go backwards and update the the case in Test Plan.

Is this correct?

2
  • What is Test Lab?
    – user246
    Aug 20, 2012 at 15:53
  • Can you add some context to this question? Is test lab a generic term or a specific product that you are referring to? Aug 20, 2012 at 17:00

1 Answer 1

3

In version 10 of Quality Center at least modifying input or expected results makes QC to ask whether you want to update the test case in Test plan. I'm not actually sure if this is the case with scripts, but I would be suprised if not.

If you answer affirmative, the test case will be checked out for you and changes are updated there. You then need to check in the changes (or discard them).

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.