The following question has appeared in several mock exams I did.
When a new testing tool is purchased, it should first be used by
- A smaller team to establish the best way to use the tool
- Everyone who may eventually have some use for the tool
- Independent Test Team
- The managers to see what projects it should be used in
- The vendor contractor to write the initial scripts
The confusing thing is that, as the answer, some exams say that
- Small Team should use the tool first
while others say that
- everyone who may eventually have a use
What do you experts think the correct answer is?
My personal belief is that
A testing tool, once purchased, should be used by a small team first to establish the best way to use it.
Or, should it be done before 'Purchasing' the tool?