Does Kanban imply the removal of bug tracking?

The software development planet is in a phase of huge transitions. There are many sdlc models being introduce and transformed like Agile , DevOps , DevSecOps and so on. One of the main shift I ...
0
votes
2answers
62 views

Definition of ready and done in an agile test environment (when test teams are not on site)

details In my current project I work with different test teams, some of which work in different time zones, and also in different projects. However, all projects work on a common main project. ...
1
vote
4answers
85 views

Are there generally accepted standards for frequency of bugs?

Are there any sort of general standards, levels or percentages for how many issues should be reopened due to a bug being found during testing? Of course this will vary but I am looking for a general ...
0
votes
3answers
85 views

How to provide Product Owner with estimates for unit testing?

"How long does it take his developer to write a unit test?" This is exactly the question the project owners keep asking me. The question is not actually how long it takes to write the unit test, but ...
-1
votes
2answers
58 views

Area of responsibility of a test manager within the agile process?

At first glance, Scrum doesn't say anything about how to test and who should take responsibility for it. Sure, it is always said that in Scrum the team is testing. But who bears the responsibility? ...
-2
votes
1answer
62 views

Test and developer of the psychological approach. Avoidance of tensions implement, but how?

Many testers are aware that sometimes it is not easy to mediate between developers and testers or to find a common approach. Sometimes, anger also tends to rule on both sides. Within ISTQB this area ...
4
votes
3answers
131 views

Have test cases evaluated by everyone in the Scrum team? Including the developers?

I am currently assigned to a new project, on a Scrum team that didn't have a tester integrated before. There are no test cases yet, but the project is more advanced. So I'm busy defining test cases ...
3
votes
2answers
106 views

How to handle bottle necks in agile testing procedures

We have a problem in our development team, the development throughput is much higher than our QA members can test. Our test team found itself in a situation where a new feature needs to be tested ...
2
votes
4answers
94 views

How do you ensure the quality of the design when the design is “by doing”?

I am convinced that an incremental design can be good. But if in the beginning a bad design is chosen and the subsequent steps are always based on it, in my opinion it can also run very badly. So ...
-1
votes
1answer
49 views

Handling Issues in a agile environment? [duplicate]

Right now I'm almost tormented by answering the following question: "How do we handle our errors and issues in an agile environment?" Scrum is a framework that does not directly dictate how to ...
4
votes
3answers
115 views

How do you prevent poorly written acceptance criteria?

One of the biggest problems from my daily work in the team is the acceptance criteria are mostly too unclearly defined. What this means in detail: Stands inquiries, because the PO or a developer has ...
14
votes
7answers
2k views

The test team as an enemy of development? And how can this be avoided?

Details Forming a Scrum team should include all the skills necessary to develop a user story in order to deliver a potentially deliverable product increment with each sprint. In traditional ...
-1
votes
1answer
33 views

Buffer for errors in the Sprint Planning Meeting?

In a discussion with a Product Owner I had the situation that there were many bugs in the Product Backlog, but PO did not have time to prioritize them. So he wanted to set a story that is timeboxed ...
9
votes
6answers
2k views

How to deal with or prevent idle in the test team?

I'm currently in two scrum projects. The team consists of 9 people (5 developers, 3 testers). We work with user stories, story point estimates and two-week sprints. The team has received a great deal ...
3
votes
1answer
191 views

What changes for testers when they are testing in agile environments?

We know that the whole development team is responsible for the quality of the product. If only the testers test, there can be no question of shared responsibility. Of course, the testers in the team ...
4
votes
4answers
127 views

What timeframe should be scheduled for exploratory testing?

Basically, the Explorative Test should be planned accordingly over a Timebox. But how do you define these? Does the team decide within the sprint planning how big the effort for the exploratory test ...
2
votes
3answers
179 views

Multiple Scrum Teams - How Can I Make Use of QA?

Currently I have two Scrum-Teams I'm responsible for, who did not plan a QA structure before. There were code reviews, and partly acceptance test. Previously, the functionality was developed within a ...
0
votes
1answer
104 views

Exploratory testing or SBTM in the Sprint Planning?

I would like to include SBTM in our sprint. Ask with, of course, many questions. Where is the difference to explorative testing? Is more worthwhile an explorative test with timebox? What times should ...
4
votes
1answer
81 views

Code freeze implementation in Scrum team

Could you, please, share your experience on test processes on your project. Do you have code freeze for the test team to retest all the stories, that were made during the sprint, on the end of a ...
1
vote
1answer
40 views

how to implement ATDD and TDD at the same time

i highly appreciate your effort to provide me with real implementation -as example- of scrum process from requirement to user story and acceptance criteria and when to start design TDD and ATDD maybe ...
3
votes
3answers
359 views

How to keep track of regression bugs during Sprint in JIRA?

I want to keep track of all the regression bugs in JIRA, which is not related to any specific user stories in the current sprint. While creating as separate bug/task in the sprint affect its scope. ...
0
votes
1answer
90 views

How to handle QA and testing in a scrum environment?

I work for a web development agency, and we are using the scrum model. The way it is applied may not be the best. We use grooming sessions, work in complexity points, but in the end, the project was ...
1
vote
2answers
97 views

Using test-cases, check-list as supporting stuff in development?

Our company is moving from waterfall to scrum. So now testers and developers are really working together. And there is an idea to use checklists and test-cases created by testers as stuff that will ...
4
votes
3answers
565 views

Should code reviewer read user story COAs?

As I understand, code review is to look for language/framework best practices, uniform conventions, guidelines and optimization paths. A while ago, I was peer reviewing code in scrum team and had some ...
11
votes
5answers
4k views

Separate QA v.s. Scrum Team Member - How should QA be involved?

(Sorry it's a long question) I have worked with several companies where QA Team is treated as part of development team, and QA team is involved in most of the activities within development process. ...
4
votes
3answers
1k views

QA Steps to move sprint story from Ready for QA to Done?

I am looking for the high level general steps performed by a QA Engineer on a scrum team using JIRA and a test management tool like Test Rail. I realize this will be different for every company but ...
7
votes
3answers
2k views

How is regression testing tracked as part of a Sprint? Is it a user story or a task?

How is regression testing tracked as part of a Sprint? Is it a user story or a task? We always do regression testing as part of a sprint; however, there is question on whether we track as a task ...
1
vote
1answer
54 views

Automated test tasks using TFS / Scrum

My group supports automated testing for our org. We have defined a process by which scrum based product teams request us to run automation against builds that are candidates for production. There is ...
4
votes
5answers
3k views

How to set up a Software testing process

I have been assigned a task to create a Testing process in the company. Our company uses Agile methodology. The task is to create a generic plan which determines the role of a QA/Tester in the ...
2
votes
3answers
806 views

Does anyone know of a good bug matrix or defect management process?

I am currently looking for a good bug matrix. Does anyone know of one, i have come across this: https://michaellant.com/2010/05/25/a-simple-agile-defect-management-process/
15
votes
6answers
6k views

How to tackle a huge bug backlog?

What is the best approach in dealing with a huge bug backlog? Currently we have a huge bug backlog and i was looking for an efficient way to deal/categorize/ how to manage the backlog?
5
votes
5answers
13k views

How Agile/Scrum Teams estimate Testing Effort?

In Agile Testing, what are some of the most common estimation techniques with context to the QA process. What are story points?
1
vote
1answer
2k views

Types of testing can be done on a first build

Today I attended an interview. These are the questions which I thought I needed more clarification. 1.What are the types of testing that can be conducted on first build which was released in first ...
6
votes
4answers
1k views

How to handle Idle team members in Sprint

I am working as a SCRUM MASTER in a TEAM of 10 people (6 DEV, 1 Designer & 3 QA). My organization has just started working in SCRUM methodology and we are having a problem in resource management - ...
3
votes
2answers
1k views

Scrum Master certification for manual tester? Boon or not?

I have learnt that a "Scrum Master" is the one who facilitates the "continuous improvement" process during a Sprint retrospective. From my experience the retrospective leads to improving the (testing) ...
5
votes
4answers
469 views

“Conventional” Test cases in an Agile environment?

i've just started at a Web Development company that does websites/mobile apps. I've done QA for 5-6 years now and they wanted someone that had QA experience but wasn't set in their ways to be their QA ...
2
votes
2answers
147 views

What should I be testing, aside from unit testing, in an agile environment?

The focus always seems to be on short stories and then the code that goes with them tends to have units tests. What other areas or levels should I be testing in? The context is for SaS (Software as ...
3
votes
2answers
165 views

What is the complete scrum process for testing a change from start to end

I need complete start to end scrum process for testing a change. From taking a bug/enhancement from the product backlog , getting a BRD/FSD, writing Test scenarios......to........logging bugs to Jira ...
6
votes
3answers
6k views

Differences between KANBAN and SCRUM with respect to testing?

Could anyone please give some important differences between KANBAN and SCRUM with respect to testing? Any examples are most welcome.
8
votes
4answers
957 views

Agile Tester vs Traditional Tester…?

What is the Difference in Role of a Traditional Manual Tester, who works in a waterfall based Project and that of an Agile tester, who works in an Agile based Project? My project has started to ...
3
votes
4answers
644 views

Blended testing strategy in agile. Is it really possible to do efficiently?

In a book I have, it says that for agile project, blended test strategy is the best, where it should use: Risk based strategy Reactive Automated regression So I was about to implement in our project ...
1
vote
1answer
354 views

Requirement-to-code traceability in Agile/Scrum development?

I'm trying to figure out how to provide an easy-to-manage requirements-to-code (and vice-versa) traceability to some projects which use SCRUM and JIRA. The projects use unit testing. So I'm splitting ...
3
votes
5answers
8k views

Test reports for Agile software releases

Our organisation and clients expects us to give a sort of test "certificate" for each release. Each release consists of a couple of three/four weeks sprints, including testing efforts as: Automated ...
2
votes
1answer
2k views

HP Agile Manager versus JIRA

Has anyone used and able to offer a comparison of HP Agile Manager versus JIRA in a scrum environment, with 2 week sprints? This is considering test management, the benefits of integrated bug tracking,...
4
votes
1answer
255 views

How do I assess the testing process of a project?

I need to asses the efficiency/productivity of a project's testing process, which also uses SCRUM. How do I go about? Are there some peer-reviewed or well-known standard approachs to evaluate the ...
5
votes
2answers
2k views

QA as Scrum Master

I have been thinking more and more as to whether it’s a good idea to have one of the Lead QA testers as the project's Scrum Master? Here’s my thinking, which may not be the same in every company/...
19
votes
7answers
1k views

In agile (Scrum) practices, where do I start with making QA (testing) more efficient if the team is transitioning from waterfall to agile?